2025 Township Capital Roads Projects
Road | From | To | Dates | Scope of Work |
---|---|---|---|---|
Wray Road | Butter and Egg Road | End | Summer 2025 |
Brushing, Ditching, Culvert Replacements and Hot Mix Resurfacing |
Carlo Enterprise Road | 1039 Carlos Enterprise Road | 170m westerly | Summer 2025 | Hot Mix Resurfacing of paved hill |
Butter & Egg Road | Lake (1540 Butter and Egg Road) | Milford Bay Road | Summer 2025 | Brushing, Ditching, Culvert Replacements and Hot Mix Resurfacing |
Walkers Point Road | District Road 30 | Marina Road | Summer 2025 | Slurry Seal |
Walkers Point Road | Marina Road | End | Summer 2025 | Slurry Seal |
Butterfly Road | Muskoka Road 169 | End | Summer 2025 | Slurry Seal |
Beatrice Townline | Muskoka Road 47 | 1690 Beatrice Townline Road (excluding Cook's Swamp) for a distance of 1.03 km | Summer 2025 | Slurry Seal |
Scarcliffe Road | Muskoka Road 118W | 150m south of Marquis Lane | Summer 2025 | Slurry Seal |
Buttler Road | Falkenburg Road | End | Summer 2025 | Slurry Seal |
Torrance Road |
Muskoka Road 169 (east junction), westerly | West Black Lake Road | Summer 2025 | Slurry Seal |
Marquis Lane | Scarcliffe Road | End | Summer 2025 | Slurry Seal |
Ziska Road | Kirrie Glenn Road | Partridge Lane (Boundary Line - Town of Bracebridge) | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Rostrevor Road | 1.1km north of Muskoka Road 4 | End | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Hemlock Point Road | Muskoka Road 7 | Hemlock Point Sideroad | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Whiteside Road | Muskoka Road 26 | End | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Big Joe Road | Hemlock Point Road | End | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Kirrie Glen Road | Muskoka Rd 118W | Ziska Road | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Surface Treatment Resurfacing |
Bear Cave Road | 1.9km north of Hekkla Road | 3.65 km north of Hekkla Road | Spring/Summer 2025 | Brushing, Ditching, Culvert Replacements and Gravel Resurfacing |
District Roads in the Township of Muskoka Lakes |
The following roads are under the jurisdiction of the District of Muskoka:
For more information view the District Road Map or contact the District of Muskoka Engineering and Public Works Department at 705-645-6764. All District Road Capital projects can be found the District of Muskoka website. |
Ministry of Transportation Roads in the Township of Muskoka Lakes |
The following roads are under the jurisdiction of the Ministry of Transportation:
For any questions or to report an issue to a road maintained by the Ministry of Transportation, you can contact them directly at 1-800-255-7814 |
Report a Concern
To report an emergency, please call 9-1-1.
Submit a question or concern through our online form. These submissions are reviewed during regular office hours. If your concern requires immediate attention, please call the municipal office at 705-765-3156. After operating hours, you will speak with our after-hours messaging service who will contact a staff member if necessary.
Contact Us